MWRA Section 89 Water Work

Contractors for the MWRA will be working on the section 89 water line repairs this summer. These repairs will be from Stoneham/Winchester line traveling down Albany street to Montvale Avenue onto Washington Street. The MWRA is upgrading the water transmission line to meet the changing needs of local communities. During this construction there will be detours and delays we have attached the current plans and schedule for this project as provided by the MWRA. Please continue to check the website as we will update the information as we receive it.

Important Public Notice
Dear Resident:
The Massachusetts Water Resources Authority (MWRA) is currently
replacing an existing Section 89 drinking water transmission line, which
travels through the Towns of Stoneham and Winchester, as well as the City
of Woburn. Importantly, the replacement pipeline will improve water supply
and provide much needed redundancy for the city and neighboring towns.
The MWRA’s contractor, P. Gioioso & Sons of Hyde Park, MA, is currently
working at night (7:00PM to 5:00AM) along Montvale Avenue and
Washington Street in the City of Woburn. Currently, night work is in the final
stages and is expected to be completed in the coming weeks.
During this time, the contractor will also start to demobilize equipment and
materials currently located on Albany Street, and the MWRA will activate
the new pipeline. Final overlay paving of Albany Street, Montvale Avenue,
and Washington Street is scheduled for a later date in 2024.
We apologize for any inconvenience encountered as a result of this project.
Should you have any questions, please do not hesitate to contact the
agency. For additional information please visit MWRA.com.
MWRA CONTACT:
Troy Wall, (617) 305-5762 or troy.wall@mwra.com

MWRA 7117 – SEC 89 REPLACEMENT PIPELINE SCHEDULE

WOBURN SCHEDULE – 12/8/2023 WASHINTON ST.

  • 36” DI PIPE 101+33-101+86. MONDAY 12-11
  • 36” DI PIPE 101+86-102+12 INSTALL AVMH 102+01. TUESDAY 12-12
  • 6” DI WATER AT UTICA, 1” WATER TO #1 UTICA. WEDNESDAY 12-13
  • DRAIN LATERAL CB1-3 TO DMH1-4. WEDNESDAY 12-13
  • INSTALL CB AND DRAIN LATERAL AT 100+45. THURSDAY 12-14
  • INSTALL DRAIN LATERAL AT 99+00. THURSDAY 12-14
  • TIE IN 36” DI FROM 102+12-102+20. FRIDAY 12-15
  • FLUSH AND CHLORINATE (DAY WORK). MONDAY 1-8-2024
  • SHIM PAVEMENT FOR WINTER.

 

MONTVALE AVE.

  • INSTALL SMH 2-8 AND 12” SEWER TO SMH 2-7. MONDAY 12-18
  • INSTALL 8” SEWER AND CLEAN OUT SMH FOR 306 MONTVALE. TUESDAY12-19
  • DRAIN REPAIR AT 95+80. TUESDAY 12-19
  • RAISE BURIED DRAIN MH AND INSTALL DRAIN LINE TO DMH 2-35. WEDNESDAY 12-20
  • INSTALL 12’’ SEWER TO SMH 2-34 20LF. THURSDAY 12-21
  • FLOW FILL 48” MWRA PIPE. FRIDAY 12-22
  • SHIM PAVEMENT FOR WINTER.

 

ALBANY ST. (DAY WORK)

  • TV SEWER LINE SMH 2-8 TO SMH3-12, SMH 2-7 TO SMH3-13. TUESDAY 12-19
  • INSTALL CB 2-4 AND LATERAL TO DMH 2-3. WEDNESDAY 1-3-2024.
  • REPAIR 8” SEWER ON ALBANY ST. THURSDAY 1-4-2024
  • SHIM PAVEMENT FOR WINTER.

 

NOTES:

  • REMOVE ALL EQUIPMENT ON ALBANY ST AND CLEAN UP BEFORE CHRISTMAS BREAK.
  • CHRISTMAS BREAK (NO CONSTRUCTION): MONDAY (12/25/23) – MONDAY (1/1/24).
  • FINAL RESTORATION: SPRING 2024 (INCLUDES WALL REPAIR AT CORNER OF UTICA ST. AND CROSSWALK AT MILL ST.).

 